If all goes according to plan, NASA could launch its heavy-lift Space Launch System rocket on its first flight around the moon by as early as Aug. 29.

That’s a big “if,” however: Workers at Kennedy Space Center in Florida still have to finish fixing and testing the rocket’s systems, including components that didn’t get fully checked out during last month’s launch rehearsal.

Cliff Lanham, senior vehicle operations manager for NASA’s Exploration Ground Systems Program, said it’ll be tricky to finish up the final test while observing all the launch constraints currently in place.

“We do have some challenges right now as we complete that test and all our final closeout work, particularly in the core stage intertank, to get to a point where we’re ready to roll out,” Lanham told reporters today.

Today’s announcement came on an auspicious day: the 53rd anniversary of the Apollo 11 moon landing.

The schedule calls for the 322-foot-tall, 3.5 million-pound rocket to roll out from the space center’s Vehicle Assembly Building on Aug. 18. That would set the stage for potential launch attempts on Aug. 29, Sept. 2 and Sept. 5. Liftoff would mark the start of NASA’s Artemis 1 mission, an uncrewed test flight that’s meant to blaze a trail for astronauts to land on the lunar surface by as early as 2025.

Artemis 1 calls for the SLS rocket to send NASA’s Orion deep-space capsule into a widely looping orbit around the moon, and then bring it back to Earth for a Pacific Ocean splashdown. The trips associated with the three launch opportunities announced today would last 39 to 42 days.

See also  Radian Aerospace comes out of stealth and raises $27.5M for orbital space plane development

Three instrument-laden mannequins — nicknamed Commander Moonikin Campos, Helga and Zohar — would provide the mission team with data about the conditions that actual astronauts would experience during a round-the-moon trip on Artemis 2 in the 2024 time frame, and during the Artemis 3 moon landing mission.

NASA will also test a digital voice assistant that’s based on Amazon’s Alexa AI software. Amazon is partnering with Lockheed Martin and Cisco on Project Callisto, which could provide astronauts with in-flight information during future Artemis missions. Lanham said the hardware for the Callisto digital assistant has already been installed in the Orion capsule.

Orion’s most critical test would come at the end of the trip.

“When Orion returns from the moon, we’ll be traveling about 24,500 miles an hour, or Mach 32, and experience temperatures half as hot as the sun outside the heat shield,” said Mike Sarafin, Artemis mission manager at NASA Headquarters.

Sarafin said the heat shield has gone through ground testing, but will face the acid test under atmospheric re-entry conditions during Artemis 1. “We could see something that we didn’t anticipate,” he said.

Jim Free, associate administrator for NASA’s Exploration Systems Development Mission Directorate, said the launch team is working its way through a to-do list that was put together after last month’s rehearsal on the launch pad — including the replacement of fuel-line seals that caused problems during the countdown.

Free emphasized that the dates released today were “not an agency commitment,” but merely a schedule for the launch team to target. “We’re here today to say, ‘Hey, we think we’re on a good path to get to attempts on those dates,’” he said.

See also  Astronomers breathe a sigh of relief after Webb Telescope unfolds its mirror in space

Once the SLS rocket is rolled out, mission planners will have to watch the clock on the onboard batteries that provide power for the flight termination system. If liftoff doesn’t occur by Sept. 5 or 6, NASA would have to wait for the next launch window — which would be open from Sept. 19 to Oct. 4 — or perhaps even the following window, which opens Oct. 17.

Related Posts

Tech founder who took space trip with William Shatner dies in N.J. plane crash

Glen de Vries peers out from Blue Origin’s New Shepard suborbital space capsule after touchdown in October. (Blue Origin Photo) A month after taking a suborbital space…

BlackSky makes a deal to sell satellite imagery to NASA — and makes its first quarterly report

One of BlackSky’s Earth observation satellites is readied for launch. (Rocket Lab Photo) BlackSky Technology says it has secured a five-year, sole-source blanket purchase agreement with NASA…

Jeff Bezos says he’s spending more on his Earth Fund than on Blue Origin space shots

Jeff Bezos, the founder of Amazon and Blue Origin, talks about the link between space and Earth’s welfare with moderator Adi Ignatius at a forum at Washington…

Orbite’s plans for space training complex get a boost from famed French designer Philippe Starck

Orbite customers and instructors take a zero-G airplane flight during spaceflight training. (Orbite Photo) The French designer who created the look for Virgin Galactic, Spaceport America and…

Rocket Lab launches two more Earth observation satellites for BlackSky — and tracks a falling rocket

Rocket Lab’s Electron launch vehicle rises from its New Zealand launch pad. (Rocket Lab via YouTube) BlackSky’s Earth-watching constellation has grown by two satellites, thanks to Rocket…

NASA begins DART mission to practice pushing away an asteroid, with an extra push from Aerojet

SpaceX’s Falcon 9 rocket launches NASA’s DART asteroid probe from Vandenberg Space Force Base in California. (NASA via YouTube) A space probe the size of a school…

Leave a Reply

Your email address will not be published. Required fields are marked *